【单选题】
An administrator has upgraded to vSphere 6.5 and also wants to use Kerberos authentication for NFS. Which can be done to the existing NFSv3 volumes to enable this feature?___
A. Perform a storage rescan on VMFS volumes.
B. Unmount the NFSv3 datastore, and then mount as NFSv4.1 datastore.
C. Nothing. All NFSv3 mounted datastores are upgraded automatically during vSphere upgrades.
D. Perform a scan of new storage devices.
查看试卷,进入试卷练习
微信扫一扫,开始刷题
答案
B
解析
暂无解析
相关试题
【单选题】
An administrator wants to restore the vCenter Server Appliance 6.5 from backup. Where can this be accomplished?___
A. from the ESXi Host Client
B. from the VMware vSphere Appliance Management Interface
C. from within the VMware vSphere Web Client
D. from the vCenter Server Appliance Installer
【单选题】
The administrator wants to power on VM-K2, which has a 2GHz CPU reservation. VM-M1, VM-M2, and VM-K1 are all powered on. VM-K2 is not powered on. The exhibit shows the parent and child resource reservations. If Resource Pool RP-KID is configured with an expandable reservation, which statement is true?___
A. VM-K2 will be unable to power on because there are insufficient resources.
B. VM-K2 will be able to power on since resource pool RP-KID has 2GHz available.
C. VM-K2 will be unable to power on because only 2GHz are reserved for RP-KID.
D. VM-K2 will receive resource priority and will be able to power on this scenario.
【单选题】
Which is the block size on the VMFS6 datastore?___
A. All small and large file blocks are 8MB.
B. All small and large file blocks are 1MB.
C. Small file blocks are 512KB. large file blocks are 64MB.
D. Small file blocks are 1MB, large file blocks are 512MB.
【单选题】
When installing vCenter Converter Standalone, why must an administrator perform a client-server installation instead of a local installation?___
A. to manage conversion tasks remotely
B. to convert virtual machines as well as physical machines
C. to allow installation of the Converter agent on remote source machines
D. to hot clone physical or virtual machines
【单选题】
Which is required by vCenter Converter Standalone to convert a physical Red Hat Enterprise Linux 7 machine to a virtual machine?___
A. The Linux machine must be powered off.
B. The Linux machine must have the SSH daemon started.
C. The Linux machine must use a static IP address.
D. The Linux machine must have a fully-qualified domain name.
【单选题】
An administrator is troubleshooting network communications between a vCenter Server and an ESXi 6.5 host. Which log shows the related events between these components?___
A. /var/log/fdm.log
B. /var/log/vpxa.log
C. /var/log/hostd.log
D. /var/log/auth.log
【单选题】
An administrator has recently upgraded from vSphere 6.0 to 6.5, and can no longer see the software iSCSI named vmhba33. Which could be the reason for this?___
A. The upgrade has changed the vmhba name.
B. vSphere 6.5 automates iSCSI configurations.
C. vSphere 6.5 no longer supports software iSCSI.
D. The upgrade has deleted the vmhba.
【单选题】
An administrator is trying to vMotion a VM from his datacenter to a recovery site. Which is the maximum allowed RTT (Round-Trip Time) latency between source and destination host?___
A. 100 milliseconds
B. 150 milliseconds
C. 15 milliseconds
D. 10 milliseconds
【单选题】
Which is required for configuring iSCSI Software Adapter network port binding?___
A. VMkernel of the iSCSI traffic must be load balanced using Route based on IP Hash algorithm.
B. VMkernel of the iSCSI traffic must be load balanced using Route based on Source Virtual Port ID algorithm.
C. VMkernel of the iSCSI traffic must be load balanced using Route based on Source MAC Hash algorithm.
D. VMkernel of the iSCSI traffic must be bound to only one active network adapter.
【单选题】
In vSphere Data Protection 6.1, which is the function of a Backup Verification job?___
A. None. Backup Verification job is not a feature of vSphere Data Protection
B. It is a manual task -Power it on -Verify the guest OS -Check started applications
C. It is an automatic process -Restore a virtual machine -Power it on -Verify that the guest OS is booted by communicating with the Backup Verification agent
D. It is an automatic process -Restore a virtual machine -Power it on -Verify that the guest OC is booted by detecting the VMware ToolsTM "heartbeats"
【单选题】
An administrator has enabled vSphere Distributed Switch Health Check. The hosts connected to that Distributed Switch all display an alert:< vSphere Distributed Switch MTU supported status > .The administrator has all of the VMkernel ports MTU sizes set to 1600. Which action will remedy this problem?___
A. Configure the Distributed Switch to MTU 9100.
B. Disconnect and reconnect the physical network cable.
C. Configure the physical switch to MTU 1600.
D. Disable the Distributed Switch MTU.
【单选题】
Which Host Profile Subprofile configuration is used to configure firewall settings for ESXi hosts?___
A. Advanced Configuration Settings
B. General System Settings
C. Security
D. Networking
【单选题】
Where would a vSphere administrator find general vCenter Server logs on a vCenter Server Appliance?___
A. /var/log/vmware/vpxd/
B. /var/log/messages
C. /etc/vmware-vpx/
D. /var/log/vmware/vsan-health/
【单选题】
An administrator wishes to enable network port mirroring based on source port. Which feature should be enabled?___
A. vSphere standard switch port
B. ERSPAN
C. NSX Virtual Wire
D. VLAN
【单选题】
Which CLI command shows the physical uplink status for a vmnic?___
A. esxcli network ip connection list
B. esxcli network ip neighbor list
C. esxcli network nic get
D. esxcli network nic list
【单选题】
Which is the maximum number of block devices (LUNs) that are supported by ESXi hosts that are running version 6.5?___
A. 1024
B. 512
C. 2048
D. 256
【单选题】
When performing a vCenter Server 5.5 for Windows with Microsoft SQL Server Express database migration to vCenter Server Appliance 6.5, which will be the target database?___
A. Microsoft SQL Server Express 2012R2
B. Microsoft SQL Server Standard 2012R2
C. PostgreSQL
D. Oracle DB 11g
【单选题】
An administrator has multiple vCenter Server 6.5 systems but cannot enable Storage I/O Control (SIOC) on a datastore shared by ESXi hosts managed by the vCenter Server systems. Which action should the administrator take to resolve the issue?___
A. Unmount the datastore and then enable SIOC on the vCenter Server system.
B. Configure the datastore to be managed by a single vCenter Server system.
C. Configure Storage DRS and then enable SIOC on the vCenter Server system.
D. Enable Raw Device Mapping (RDM) on the
E. SXi hosts.
【单选题】
“OneAppServer” is a VM template stored in a content library named “LibraryOne”, but the vSphere administrator is not able to use this template for deployment. Why is the administrator unable to deploy OneAppServer?___
A. OneAppServer must be updated before it can be deployed.
B. LibraryOne is a subscribed library and OneAppServer is not downloaded yet.
C. LibraryOne is published and optimized for syncing over HTTP.
D. OneAppServer was imported from a local file on the system.
【单选题】
An administrator sets the Failover Capacity for both CPU and Memory at 25%. Based on the Exhibit below, how much of the cluster’s total CPU resources are still available to power on additional virtual machines?___
A. 45%
B. 25%
C. 70%
D. 60%
【单选题】
Which statement applies to the vSphere Replication appliance?___
A. Only one vSphere Replication appliance can be deployed per vCenter Server instance.
B. VMware Tools in the vSphere Replication appliance can be upgraded.
C. A single vSphere Replication appliance can manage a maximum of 4000 replications.
D. vSphere Replication is available only with the vSphere
E. ssentials Plus license.
【单选题】
Which esxcli namespace can a vSphere Administrator use to adjust the queue depth?___
A. esxcli system module parameters
B. esxcli storage core device
C. esxcli system module set
D. esxcli storage core adapter
【单选题】
Which statement regarding datastore clusters meets VMware’s recommended best practices?___
A. Clusters should contain only datastores presented from the same storage array.
B. Clusters should contain only datastores with equal hardware acceleration capability.
C. Clusters should contain only datastores with the same capacity.
D. Clusters should contain only datastores using the same connection method (iSCSI, FC, etc.).
【单选题】
What VM Monitoring setting would ensure that the maximum reset window for a virtual machine is 24 hours?___
A. Medium
B. Low
C. High
D. Normal
【单选题】
What is the default space threshold for vSphere Storage DRS?___
A. 80%
B. 70%
C. 90%
D. 95%
【单选题】
Which is the correct sequence to upgrade a vSphere infrastructure?___
A. vCenter Server>ESXi host> VMware Tools>VM compatibility
B. ESXi host>vCenter Server> VMware Tools>VM compatibility
C. vCenter host> ESXi host> VM compatibility> VMware Tools
D. ESXi host>vCenter Server> VM compatibility>VMware Tools
【单选题】
An administrator has a large boot from SAN cluster and wants to ensure consistent configuration by using host profiles. What special considerations are required for boot from SAN hosts?___
A. Change the “Device is shared clusterwide” setting to “false” in the host profile.
B. Verify that the boot LUN is correctly identified as the boot device in the host profile.
C. The boot from SAN device must report as a local device.
D. Host profiles are incompatible with boot from SAN hosts.
【单选题】
When using VMware Converter to import a Windows server and improve the consistency of the destination virtual machine, which optional step can be performed immediately prior to powering down the source server?___
A. Perform a final synchronization task.
B. Remove the server from the network.
C. Uninstall production applications.
D. Remove the server from the Active Directory domain.
【单选题】
Restoration of the vCenter Server Appliance is accomplished using which interface?___
A. vSphere Web Client
B. vSphere Client
C. vCenter Server Appliance Management Interface
D. vCenter Server Appliance GUI Installer
【单选题】
When attempting to migrate a virtual machine to another host in the same cluster, the error message, “Select a valid compute resource” returns. What could cause this error?___
A. Both hosts run different versions of ESXi.
B. Both hosts are not sharing the same datastore.
C. VMware Tools is not installed.
D. Virtual machine has an ISO attached.
【单选题】
When will vSphere Data Protection delete the expired backup image of a Platform Service Controller?___
A. Immediately after the retention period has expired.
B. After the expired backup image is restored.
C. During the next backup window following expiry.
D. During the next maintenance window following expiry.
【单选题】
Group A has permission to download files in Content Library. Group B does not have permission to download files in Content Library. If a user is a member of both groups, what will be the result?___
A. The user cannot download file from Content Library.
B. The user can download file from Content Library.
C. The user cannot access Content Library.
D. The user can access Content Library.
【单选题】
An administrator is trying to set up Host Partial Failure Response, but the Automated option is grayed out. What can the administrator change to enable the Automated option?___
A. Change the vSphere DRS Automation level to Partially Automated.
B. Change the vSphere DRS Automation level to Fully Automated.
C. Enable vSphere HA Host Monitoring.
D. Change the vSphere DPM Automation level to Automatic.
【单选题】
When you attempt to open a virtual machine console from the vSphere Web Client, the console does not connect. The following error message appears:<HTTP ERROR 404> <Problem accessin/.Reason: Not Found>. Why did not connect?___
A. Port 443 is in use.
B. Port 9443 is in use.
C. Port 8443 is in use.
D. Port 22443 is in use.
【单选题】
What new feature was introduced to the Content Library in vSphere 6.5?___
A. Mount an ISO directly from the Content Library.
B. Deploy a virtual machine from an OVF Package in a Content Library.
C. Upload a File from a URL to a Library Item.
D. Upload a File from a Local System to a Library Item.
【单选题】
How can an administrator exclude Encryption rights from a support engineer?___
A. Clone the role Virtual machine power user, remove Cryptographic operations privileges.
B. Clone the role Administrator and assign to the support engineer.
C. Clone the role Virtual machine power user and assign to the support engineer.
D. Clone the role No cryptography administrator and select privileges only for the support engineer.
【单选题】
The administrator must back up a vCenter HA deployment. Which component must be backed up?___
A. Passive node
B. Witness node
C. External database
D. Active node
【单选题】
What is the supported protocol to perform remote L3 traffic monitoring in vSphere 6.5?___
A. VXLAN
B. ERSPAN
C. RSPAN
D. SPAN
【单选题】
What are the minimum hardware requirements for a Windows vCenter Server with embedded PSC that manages a “Small” environment?___
A. 2vCPUs, 16 GB RAM
B. 4 vCPUs, 16 GB RAM
C. 2 vCPUs, 10 GB RAM
D. 4 vCPUs, 10 GB RAM
【单选题】
Which port is used for communication between ESXi and vSphere Data protection?___
A. 80
B. 443
C. 902
D. 22
推荐试题
【多选题】
按审查书面资料的技术分为___。
A. 核对法
B. 审阅法
C. 复算法
D. 比较法
E. 分析法
【多选题】
审计质量评价结果分为___。
A. 优秀
B. 良好
C. 合格
D. 不合格
【多选题】
评价审计项目操作程序质量,主要对审计项目是否严格按照操作规程情况进行评价,包括___。
A. 立项情况
B. 谈话询证情况
C. 人员组织情况
D. 审前调查情况
E. 审计证据质量
F. 审计底稿质量
【多选题】
整改工作应遵循以下原则___。
A. 有错必纠原则
B. 责任落实原则
C. 标本兼治原则
D. 及时性、真实性、有效性原则
E. 持续改进原则
【多选题】
整改责任单位职责如下___。
A. 制订整改计划,明确具体整改责任人
B. 执行审定后的整改计划,落实各项整改措施
C. 建立整改台账,实行整改销号
D. 确保问题不整改不放过,责任追究不到位不放过
E. 按时报告整改工作进展及落实情况
F. 配合后续审计工作
【多选题】
编制审计报告的基本原则为___。
A. 坚持原则,实事求是
B. 内容完整、重点突出
C. 事实清楚,数据真实
D. 层次清晰,结构合理
E. 证据充分,定性准确
F. 文字简练,表述准确
【多选题】
审计报告封面包括下列基本要素___。
A. 标题
B. 文号
C. 被审计单位名称
D. 审计项目名称
E. 审计组名称及审计组组长签名
F. 签发日期
【多选题】
审计取证单(事实确认书)主要内容包括___。
A. 审计项目名称
B. 被审计单位名称
C. 审计事项名称
D. 审计事项事实摘要
E. 证据提供单位及负责人意见
【多选题】
审计组成员应当对以下哪些事项承担责任?___
A. 未严格按照方案实施审计导致重大问题未被发现的
B. 未按照本规程的要求获取审计证据导致审计证据不适当、不充分的
C. 审计记录不真实、不完整的
D. 对发现的重要问题隐瞒不报或者不如实报告的
E. 未经同意擅自脱离检查工作岗位,影响正常工作的
F. 擅自向与检查事项无关人员透露应保密的检查内容和发现事项的
【多选题】
本规程所称重大问题是指被审计单位和相关人员违反法律法规、涉及金额比较大的、造成国家和农信社重大经济损失或者性质特别恶劣的行为。主要包括但不限于以下行为___
A. 涉及群众实名举报重大违规违纪问题或审计中发现经济案件线索的
B. 涉及可能应当追究有关领导人员、直接责任人员行政、组织、刑事责任线索的
C. 涉及挪用或者克扣职工工资、职工福利费等专项资金数额巨大、情节严重的
D. 单位负责人强制下属人员违反财经法规的
E. 涉及重要审计证据可能被灭失的
F. 拒不提供或者故意提供虚假会计资料的
【多选题】
审计整改工作应遵循的原则?___
A. 有错必纠原则
B. 责任落实原则
C. 标本兼治原则
D. 及时性原则
E. 真实性原则
F. 有效性原则
【多选题】
年度行业审计计划的内容主要包括?___
A. 审计项目名称
B. 审计目标
C. 审计范围
D. 审计成本
E. 审计重点
F. 审计项目实施时间
【多选题】
审计计划编制应遵循的基本原则?___
A. 审计价值最大化
B. 项目管理一体化
C. 利润最大化
D. 质量控制流程化
E. 风险最小化
F. 成本最低化
【多选题】
审计部门编制年度审计计划应综合考虑以下哪些因素?___
A. 年度主要工作目标、工作重点
B. 辖内法人机构风险评估、内部控制情况
C. 人民银行、国家审计部门、监管部门要求
D. 理事会、高级管理层的经营管理需要
E. 审计室(区域审计中心)制订的审计计划
F. 上年度审计情况和后续审计的必要安排
【多选题】
审计的主要程序?___
A. 审计准备
B. 审计实施
C. 重大问题督办
D. 结束现场审计
E. 审计报告
F. 装订档案
【多选题】
审计准备阶段的流程?___
A. 审计立项
B. 制定审计方案
C. 组建审计组
D. 开展审前培训
E. 进驻现场
F. 送达审计通知书
【多选题】
审计方案应包括的基本内容?___
A. 审计目的
B. 审计对象
C. 审计开支
D. 审计内容
E. 审计范围
F. 审计依据
【多选题】
审计通知书的基本内容?___
A. 审计对象名称
B. 审计项目名称
C. 审计范围
D. 审计开始时间
E. 审计组成员名单
F. 审计要求
【多选题】
审计实施的主要环节?___
A. 签订承诺书
B. 召开进点会议
C. 发布审计公告
D. 审计取证
E. 编制审计工作底稿
F. 汇总审计结果
【多选题】
审计工作底稿的主要内容?___
A. 被审计单位名称
B. 审计内容
C. 审计过程和结论
D. 审核人员姓名、审核意见及审核日期并签名
E. 索引号及页码
F. 审计费用
【多选题】
编制审计报告的基本原则?___
A. 坚持原则,实事求是
B. 内容完整,重点突出
C. 事实清楚,数据真实
D. 层次清晰,结构合理
E. 证据充分,定性准确
F. 文字简练,表述准确
【多选题】
审计报告封面应包括的基本要素?___
A. 标题
B. 文号
C. 被审计单位名称
D. 审计项目名称
E. 审计组名称及审计组组长签名
F. 签发日期(审计组提交报告的日期)
【多选题】
审计报告的主要内容?___
A. 审计项目实施情况
B. 审计花费情况
C. 被审计单位的基本情况
D. 审计评价意见
E. 审计发现的主要问题
F. 审计建议
【多选题】
整改责任单位的职责?___
A. 制订整改计划,明确具体整改责任人
B. 执行审定后的整改计划,落实各项整改措施
C. 建立整改台账,实行整改销号
D. 确保问题不整改不放过,责任追究不到位不放过
E. 按时报告整改工作进展及落实情况
F. 配合后续审计工作
【多选题】
审计组组长应当对审计工作底稿的哪些事项进行审核?___
A. 具体审计目标是否实现
B. 审计程序是否有效执行
C. 事实是否清楚
D. 审计证据是否适当、充分
E. 得出的审计结论及其相关标准是否适当
F. 其他有关重要事项
【多选题】
行业审计的目标是___
A. 推动有关经济金融法律法规和监管规则的有效落实
B. 强化对全省农信社经营管理、内部控制、风险状况进行持续监督
C. 促进全系统法人行社建立并持续完善有效的风险管理、内控合规和公司治理架构
D. 实现农信社(农商银行)的战略发展目标
【多选题】
年度行业审计计划的内容主要包括:___。
A. 审计项目名称
B. 审计目标
C. 审计范围
D. 审计重点
E. 审计项目实施时间
F. 审计资源配置
【多选题】
审计准备是指审计部门为开展审计项目提前应做好的工作,主要包括___。
A. 审计立项
B. 制定审计方案
C. 组建审计组
D. 审前培训
E. 签发和送达审计通知
【多选题】
审计调查的方法包括___
A. 外核法
B. 查询法
C. 函证法
D. 直接法
【多选题】
按审查书面资料的技术分为___。
A. 核对法
B. 审阅法
C. 复算法
D. 比较法
E. 分析法
【多选题】
审计质量评价结果分为___。
A. 优秀
B. 良好
C. 合格
D. 不合格
【多选题】
评价审计项目操作程序质量,主要对审计项目是否严格按照操作规程情况进行评价,包括___。
A. 立项情况
B. 谈话询证情况
C. 人员组织情况
D. 审前调查情况
E. 审计证据质量
F. 审计底稿质量
【多选题】
整改工作应遵循以下原则___。
A. 有错必纠原则
B. 责任落实原则
C. 标本兼治原则
D. 及时性、真实性、有效性原则
E. 持续改进原则
【多选题】
整改责任单位职责如下___。
A. 制订整改计划,明确具体整改责任人
B. 执行审定后的整改计划,落实各项整改措施
C. 建立整改台账,实行整改销号
D. 确保问题不整改不放过,责任追究不到位不放过
E. 按时报告整改工作进展及落实情况
F. 配合后续审计工作
【多选题】
编制审计报告的基本原则为___。
A. 坚持原则,实事求是
B. 内容完整、重点突出
C. 事实清楚,数据真实
D. 层次清晰,结构合理
E. 证据充分,定性准确
F. 文字简练,表述准确
【多选题】
审计报告封面包括下列基本要素___。
A. 标题
B. 文号
C. 被审计单位名称
D. 审计项目名称
E. 审计组名称及审计组组长签名
F. 签发日期
【多选题】
审计取证单(事实确认书)主要内容包括___。
A. 审计项目名称
B. 被审计单位名称
C. 审计事项名称
D. 审计事项事实摘要
E. 证据提供单位及负责人意见
【多选题】
审计组成员应当对以下哪些事项承担责任?___
A. 未严格按照方案实施审计导致重大问题未被发现的
B. 未按照本规程的要求获取审计证据导致审计证据不适当、不充分的
C. 审计记录不真实、不完整的
D. 对发现的重要问题隐瞒不报或者不如实报告的
E. 未经同意擅自脱离检查工作岗位,影响正常工作的
F. 擅自向与检查事项无关人员透露应保密的检查内容和发现事项的
【多选题】
本规程所称重大问题是指被审计单位和相关人员违反法律法规、涉及金额比较大的、造成国家和农信社重大经济损失或者性质特别恶劣的行为。主要包括但不限于以下行为___
A. 涉及群众实名举报重大违规违纪问题或审计中发现经济案件线索的
B. 涉及可能应当追究有关领导人员、直接责任人员行政、组织、刑事责任线索的
C. 涉及挪用或者克扣职工工资、职工福利费等专项资金数额巨大、情节严重的
D. 单位负责人强制下属人员违反财经法规的
E. 涉及重要审计证据可能被灭失的
F. 拒不提供或者故意提供虚假会计资料的
【多选题】
审计机关依照法律规定的职权和程序,进行审计监督。审计机关依据有关___进行审计评价,在法定职权范围内作出审计决定。
A. 财政收支
B. 财务收支的法律
C. 法规
D. 国家其他有关规定
E. 审计文件